Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredCompletion date passedMahaRERA status: Certificate Signed

P51800009310

Building on Plot bearing CTS No 833 pt at MHADA layout as RNA Continental Subhash Nagar Mumbai 71 · Kurla, Mumbai Suburban · G A Builders Pvt Ltd

Promised for 31 Jan 2021 — that date has passed and MahaRERA does not mark the project complete.

5 years and 9 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 31 Jan 2021, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate18 May 2020View

Orders 0

No MahaRERA order or list names this number.

Questions about P51800009310

Is Building on Plot bearing CTS No 833 pt at MHADA layout as RNA Continental Subhash Nagar Mumbai 71 delayed?

Yes. MahaRERA records a promised completion of 31 Jan 2021, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P51800009310.

Who is the promoter?

MahaRERA records G A Builders Pvt Ltd as the promoter of P51800009310.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51800009310.

Answers are generated from the record.

Data through25 Oct 2026, 02:06SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology