RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P51800008986

Balaji Enclave · Borivali, Mumbai Suburban · Balaji Enterprise

Promised for 31 Jan 2019, extended once to 31 Jul 2024 — and that date has passed without the project marked complete on MahaRERA.

7 years and 9 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Jan 2019 to 31 Jul 2024 (1 extension certificate on record).
  • Risk: The latest completion date on record, 31 Jul 2024, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate19 Aug 2017View
Extension certificate9 Sep 2021View

Orders 0

No MahaRERA order or list names this number.

Questions about P51800008986

Is Balaji Enclave delayed?

Yes. MahaRERA records a promised completion of 31 Jan 2019, revised to 31 Jul 2024, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P51800008986. The completion date moved from 31 Jan 2019 to 31 Jul 2024.

Who is the promoter?

MahaRERA records Balaji Enterprise as the promoter of P51800008986.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51800008986.