RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P51800005041
Santoor Residency · Andheri, Mumbai Suburban · Spade Realtors Llp
Promised for 31 Mar 2018, extended once to 31 Mar 2021 — and that date has passed without the project marked complete on MahaRERA.
8 years and 7 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 31 Mar 2018 to 31 Mar 2021 (1 extension certificate on record).
- !Risk: The latest completion date on record, 31 Mar 2021, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P51800005041
Is Santoor Residency delayed?
Yes. MahaRERA records a promised completion of 31 Mar 2018, revised to 31 Mar 2021, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P51800005041. The completion date moved from 31 Mar 2018 to 31 Mar 2021.
Who is the promoter?
MahaRERA records Spade Realtors Llp as the promoter of P51800005041.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P51800005041.
Answers are generated from the record.
