RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P51800003202
Avanya · Borivali, Mumbai Suburban · Aniline Properties Private Limited
Promised for 30 Dec 2023, extended once to 30 Jun 2024 — and that date has passed without the project marked complete on MahaRERA.
2 years and 10 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 30 Dec 2023 to 30 Jun 2024 (1 extension certificate on record).
- !Risk: The latest completion date on record, 30 Jun 2024, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P51800003202
Is Avanya delayed?
Yes. MahaRERA records a promised completion of 30 Dec 2023, revised to 30 Jun 2024, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P51800003202. The completion date moved from 30 Dec 2023 to 30 Jun 2024.
Who is the promoter?
MahaRERA records Aniline Properties Private Limited as the promoter of P51800003202.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P51800003202.
Answers are generated from the record.
