Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P51800003133
A-14, A Wing Petunia Apts, Bindra Complex · Andheri, Mumbai Suburban · Accord Land Developers Pvt Ltd
Promised for 1 Nov 2018 — that date has passed and MahaRERA does not mark the project complete.
7 years and 11 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Risk: The latest completion date on record, 1 Nov 2018, has passed.
- ✓Clear: Completion date never extended.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 1
Orders 0
No MahaRERA order or list names this number.
Questions about P51800003133
Is A-14, A Wing Petunia Apts, Bindra Complex delayed?
Yes. MahaRERA records a promised completion of 1 Nov 2018, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 0 extension certificates for P51800003133.
Who is the promoter?
MahaRERA records Accord Land Developers Pvt Ltd as the promoter of P51800003133.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P51800003133.
Answers are generated from the record.