Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P51800002748

Natasha Avenue · Kurla, Mumbai Suburban · Natasha Enterprises

Promised for 30 Dec 2023, extended once to 29 Dec 2024 — and that date has passed without the project marked complete on MahaRERA.

2 years and 10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Dec 2023 to 29 Dec 2024 (1 extension certificate on record).
  • Risk: The latest completion date on record, 29 Dec 2024, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate9 Sep 2021View
Extension certificate21 Jun 2024View

Orders 0

No MahaRERA order or list names this number.

Questions about P51800002748

Is Natasha Avenue delayed?

Yes. MahaRERA records a promised completion of 30 Dec 2023, revised to 29 Dec 2024, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P51800002748. The completion date moved from 30 Dec 2023 to 29 Dec 2024.

Who is the promoter?

MahaRERA records Natasha Enterprises as the promoter of P51800002748.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51800002748.

Answers are generated from the record.

Data through25 Oct 2026, 01:55SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology