Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P51800002656

Enigma Towers A and B · Kurla, Mumbai Suburban · Oberoi Constructions Limited

Promised for 30 Dec 2022, extended once to 1 Aug 2024 — and that date has passed without the project marked complete on MahaRERA.

3 years and 10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Dec 2022 to 1 Aug 2024 (1 extension certificate on record).
  • Risk: The latest completion date on record, 1 Aug 2024, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate9 Sep 2021View
Extension certificate20 Mar 2025View

Orders 0

No MahaRERA order or list names this number.

Questions about P51800002656

Is Enigma Towers A and B delayed?

Yes. MahaRERA records a promised completion of 30 Dec 2022, revised to 1 Aug 2024, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P51800002656. The completion date moved from 30 Dec 2022 to 1 Aug 2024.

Who is the promoter?

MahaRERA records Oberoi Constructions Limited as the promoter of P51800002656.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51800002656.

Answers are generated from the record.

Data through25 Oct 2026, 01:56SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology