Monticello · Andheri, Mumbai Suburban · Samudra Developers Private Limited
Promised for 30 Nov 2019, extended once to 29 Sep 2022 — and that date has passed without the project marked complete on MahaRERA.
6 years and 11 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 30 Nov 2019 to 29 Sep 2022 (1 extension certificate on record).
- !Risk: The latest completion date on record, 29 Sep 2022, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P51800002198
Is Monticello delayed?
Yes. MahaRERA records a promised completion of 30 Nov 2019, revised to 29 Sep 2022, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P51800002198. The completion date moved from 30 Nov 2019 to 29 Sep 2022.
Who is the promoter?
MahaRERA records Samudra Developers Private Limited as the promoter of P51800002198.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P51800002198.