RegisteredCompletion date passedMahaRERA status: Certificate Signed

P51800001959

Basera Chs Ltd · Andheri, Mumbai Suburban · Lakshmi Builders And Developers

Promised for 1 Jul 2023 — that date has passed and MahaRERA does not mark the project complete.

3 years and 3 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: The latest completion date on record, 1 Jul 2023, has passed.

Documents 1

Registration certificate9 Sep 2021View

Orders 0

No MahaRERA order or list names this number.

Questions about P51800001959

Is Basera Chs Ltd delayed?

Yes. MahaRERA records a promised completion of 1 Jul 2023, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P51800001959.

Who is the promoter?

MahaRERA records Lakshmi Builders And Developers as the promoter of P51800001959.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51800001959.

Answers are generated from the record.