RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P51800001779

Montesouth · Ward E, Mumbai City · Swayam Realtors & Traders Llp

Promised for 30 Dec 2022, extended once to 29 Dec 2023 — and that date has passed without the project marked complete on MahaRERA.

3 years and 10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Dec 2022 to 29 Dec 2023 (1 extension certificate on record).
  • Risk: The latest completion date on record, 29 Dec 2023, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate9 Sep 2021View
Extension certificate1 Dec 2022View

Orders 0

No MahaRERA order or list names this number.

Questions about P51800001779

Is Montesouth delayed?

Yes. MahaRERA records a promised completion of 30 Dec 2022, revised to 29 Dec 2023, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P51800001779. The completion date moved from 30 Dec 2022 to 29 Dec 2023.

Who is the promoter?

MahaRERA records Swayam Realtors & Traders Llp as the promoter of P51800001779.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51800001779.

Answers are generated from the record.

Data through25 Oct 2026, 01:48SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology