Ekta Maplewood · Andheri, Mumbai Suburban · Ekta Housing Private Limited
Promised for 30 Jun 2018, extended once to 30 Jun 2019 — and that date has passed without the project marked complete on MahaRERA.
8 years and 4 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 30 Jun 2018 to 30 Jun 2019 (1 extension certificate on record).
- !Risk: The latest completion date on record, 30 Jun 2019, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P51800001523
Is Ekta Maplewood delayed?
Yes. MahaRERA records a promised completion of 30 Jun 2018, revised to 30 Jun 2019, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P51800001523. The completion date moved from 30 Jun 2018 to 30 Jun 2019.
Who is the promoter?
MahaRERA records Ekta Housing Private Limited as the promoter of P51800001523.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P51800001523.