RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P51800000359

Parmar Heritage · Andheri, Mumbai Suburban · Jitendra

Promised for 17 Jun 2022, extended once to 31 Mar 2026 — and that date has passed without the project marked complete on MahaRERA.

4 years and 4 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 17 Jun 2022 to 31 Mar 2026 (1 extension certificate on record).
  • Risk: The latest completion date on record, 31 Mar 2026, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate30 Jun 2023View
Extension certificate2 Aug 2023View

Orders 0

No MahaRERA order or list names this number.

Questions about P51800000359

Is Parmar Heritage delayed?

Yes. MahaRERA records a promised completion of 17 Jun 2022, revised to 31 Mar 2026, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P51800000359. The completion date moved from 17 Jun 2022 to 31 Mar 2026.

Who is the promoter?

MahaRERA records Jitendra as the promoter of P51800000359.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51800000359.