RegisteredMahaRERA status: Certificate Signed

P51700079016

Mangalmurti Heights · Bhiwandi (M Corp.), Thane · Roshni Builders And Developers

Promised for 30 Sep 2028 and not extended so far.

1 year and 11 months to go until the promised date.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate27 Jun 2025View
Registration certificate9 Oct 2026View

Orders 0

No MahaRERA order or list names this number.

Questions about P51700079016

Is Mangalmurti Heights delayed?

Not so far. MahaRERA records a promised completion of 30 Sep 2028, which has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for P51700079016.

Who is the promoter?

MahaRERA records Roshni Builders And Developers as the promoter of P51700079016.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51700079016.