Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredExtendedMahaRERA status: Certificate Signed

P51700078533

Galaxy Tower · Shahapur, Thane · Eamkay Enterprises

Promised for 31 Dec 2026, extended to 30 Apr 2027, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Dec 2026 to 30 Apr 2027.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate21 Dec 2024View

Orders 0

No MahaRERA order or list names this number.

Questions about P51700078533

Is Galaxy Tower delayed?

Its completion moved from 31 Dec 2026 to 30 Apr 2027; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for P51700078533. The completion date moved from 31 Dec 2026 to 30 Apr 2027.

Who is the promoter?

MahaRERA records Eamkay Enterprises as the promoter of P51700078533.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51700078533.

Answers are generated from the record.

Data through30 Oct 2026, 02:58SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology