RegisteredExtendedMahaRERA status: Certificate Signed

P51700077991

Sunraj Solitaire · Golivali, Thane · Sunraj Construction

Promised for 31 Dec 2031, extended to 30 Apr 2032, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Dec 2031 to 30 Apr 2032.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate21 Aug 2026View

Orders 0

No MahaRERA order or list names this number.

Questions about P51700077991

Is Sunraj Solitaire delayed?

Its completion moved from 31 Dec 2031 to 30 Apr 2032; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for P51700077991. The completion date moved from 31 Dec 2031 to 30 Apr 2032.

Who is the promoter?

MahaRERA records Sunraj Construction as the promoter of P51700077991.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51700077991.

Answers are generated from the record.

Data through25 Oct 2026, 03:24SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology