RegisteredCompletion date passedMahaRERA status: Certificate Signed

P51700048408

Lodha Panacea III · Bhopar, Thane · Lodha Developers Limited

Promised for 30 Jun 2026 — that date has passed and MahaRERA does not mark the project complete.

4 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: The latest completion date on record, 30 Jun 2026, has passed.

Documents 1

Registration certificate19 Jun 2026View

Orders 0

No MahaRERA order or list names this number.

Questions about P51700048408

Is Lodha Panacea III delayed?

Yes. MahaRERA records a promised completion of 30 Jun 2026, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P51700048408.

Who is the promoter?

MahaRERA records Lodha Developers Limited as the promoter of P51700048408.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51700048408.

Answers are generated from the record.

Data through23 Oct 2026, 02:13SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology