RegisteredMahaRERA status: Certificate Signed

P51700048334

DGT Sector 3A · Purne (Ct), Thane · Adrika Developers Private Limited

Promised for 31 Dec 2027 and not extended so far.

1 year and 2 months to go until the promised date.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate26 Dec 2022View

Orders 0

No MahaRERA order or list names this number.

Questions about P51700048334

Is DGT Sector 3A delayed?

Not so far. MahaRERA records a promised completion of 31 Dec 2027, which has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for P51700048334.

Who is the promoter?

MahaRERA records Adrika Developers Private Limited as the promoter of P51700048334.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51700048334.

Answers are generated from the record.

Data through30 Oct 2026, 02:49SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology