P51700032501
Laaman Industrial Park · Thane (M Corp.), Thane · Laaman Developers
Promised for 31 Dec 2024, extended once to 9 Jan 2025 — and that date has passed without the project marked complete on MahaRERA.
1 year and 10 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 31 Dec 2024 to 9 Jan 2025 (1 extension certificate on record).
- !Risk: The latest completion date on record, 9 Jan 2025, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P51700032501
Is Laaman Industrial Park delayed?
Yes. MahaRERA records a promised completion of 31 Dec 2024, revised to 9 Jan 2025, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P51700032501. The completion date moved from 31 Dec 2024 to 9 Jan 2025.
Who is the promoter?
MahaRERA records Laaman Developers as the promoter of P51700032501.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P51700032501.