Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P51700032369

Aadinath Complex · Asangaon (Ct), Thane · Green Heights Infra

Promised for 31 Jan 2024, extended once to 31 Dec 2025 — and that date has passed without the project marked complete on MahaRERA.

2 years and 9 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Jan 2024 to 31 Dec 2025 (1 extension certificate on record).
  • Caution: The latest completion date on record, 31 Dec 2025, has passed.

Documents 2

Registration certificate29 Dec 2021View
Extension certificate11 Apr 2025View

Orders 0

No MahaRERA order or list names this number.

Questions about P51700032369

Is Aadinath Complex delayed?

Yes. MahaRERA records a promised completion of 31 Jan 2024, revised to 31 Dec 2025, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P51700032369. The completion date moved from 31 Jan 2024 to 31 Dec 2025.

Who is the promoter?

MahaRERA records Green Heights Infra as the promoter of P51700032369.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51700032369.

Answers are generated from the record.

Data through25 Oct 2026, 02:58SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology