Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P51700030070

Vakratunda Homes · Washind (Ct), Thane · Narayan Sunil Rane

Promised for 31 Dec 2023, extended once to 30 Dec 2024 — and that date has passed without the project marked complete on MahaRERA.

2 years and 10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Dec 2023 to 30 Dec 2024 (1 extension certificate on record).
  • Caution: The latest completion date on record, 30 Dec 2024, has passed.

Documents 2

Registration certificate29 Jul 2021View
Extension certificate2 Apr 2024View

Orders 0

No MahaRERA order or list names this number.

Questions about P51700030070

Is Vakratunda Homes delayed?

Yes. MahaRERA records a promised completion of 31 Dec 2023, revised to 30 Dec 2024, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P51700030070. The completion date moved from 31 Dec 2023 to 30 Dec 2024.

Who is the promoter?

MahaRERA records Narayan Sunil Rane as the promoter of P51700030070.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51700030070.

Answers are generated from the record.

Data through24 Oct 2026, 02:25SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology