Registered1 extensionMahaRERA status: Certificate Signed

P51700029534

Constrcution of 2557 EWS tenements at S.No.157/1,village Gotheghar,Tal . Dist.-Thane PMAY Project · Goteghar, Thane · Arun Shankarrao Borgave

Promised for 8 Mar 2023, extended once to 6 Jun 2028, which is still ahead.

The revised date is 5 years and 3 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 8 Mar 2023 to 6 Jun 2028 (1 extension certificate on record).
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate4 Jun 2021View
Extension certificate1 Dec 2023View

Orders 0

No MahaRERA order or list names this number.

Questions about P51700029534

Is Constrcution of 2557 EWS tenements at S.No.157/1,village Gotheghar,Tal . Dist.-Thane PMAY Project delayed?

Its completion moved from 8 Mar 2023 to 6 Jun 2028; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 1 extension certificate for P51700029534. The completion date moved from 8 Mar 2023 to 6 Jun 2028.

Who is the promoter?

MahaRERA records Arun Shankarrao Borgave as the promoter of P51700029534.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51700029534.

Answers are generated from the record.

Data through28 Oct 2026, 02:31SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology