RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P51700025122

Motiram Darshan Nx - 1 · Ambarnath(M Cl), Thane · Shree Heramb Builders

Promised for 30 Sep 2024, extended once to 30 Sep 2025 — and that date has passed without the project marked complete on MahaRERA.

2 years and 1 month past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Sep 2024 to 30 Sep 2025 (1 extension certificate on record).
  • Risk: The latest completion date on record, 30 Sep 2025, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate29 May 2024View
Extension certificate29 May 2024View

Orders 0

No MahaRERA order or list names this number.

Questions about P51700025122

Is Motiram Darshan Nx - 1 delayed?

Yes. MahaRERA records a promised completion of 30 Sep 2024, revised to 30 Sep 2025, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P51700025122. The completion date moved from 30 Sep 2024 to 30 Sep 2025.

Who is the promoter?

MahaRERA records Shree Heramb Builders as the promoter of P51700025122.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51700025122.

Answers are generated from the record.

Data through25 Oct 2026, 02:50SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology