RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P51700021362
Sagar Homes · Ranjnoli, Thane · Sagar Developers
Promised for 30 Dec 2023, extended once to 29 Dec 2025 — and that date has passed without the project marked complete on MahaRERA.
2 years and 10 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 30 Dec 2023 to 29 Dec 2025 (1 extension certificate on record).
- !Caution: The latest completion date on record, 29 Dec 2025, has passed.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P51700021362
Is Sagar Homes delayed?
Yes. MahaRERA records a promised completion of 30 Dec 2023, revised to 29 Dec 2025, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P51700021362. The completion date moved from 30 Dec 2023 to 29 Dec 2025.
Who is the promoter?
MahaRERA records Sagar Developers as the promoter of P51700021362.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P51700021362.
Answers are generated from the record.
