RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P51700021264

Orient Legacy · Badlapur (M Cl), Thane · Jewel Orient

Promised for 30 Dec 2024, extended once to 30 Jun 2025 — and that date has passed without the project marked complete on MahaRERA.

1 year and 10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Dec 2024 to 30 Jun 2025 (1 extension certificate on record).
  • Risk: The latest completion date on record, 30 Jun 2025, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate5 Sep 2022View
Extension certificate26 Mar 2025View

Orders 0

No MahaRERA order or list names this number.

Questions about P51700021264

Is Orient Legacy delayed?

Yes. MahaRERA records a promised completion of 30 Dec 2024, revised to 30 Jun 2025, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P51700021264. The completion date moved from 30 Dec 2024 to 30 Jun 2025.

Who is the promoter?

MahaRERA records Jewel Orient as the promoter of P51700021264.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51700021264.

Answers are generated from the record.

Data through28 Oct 2026, 03:28SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology