RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P51700018798
Sunset Heights 2 · Badlapur (M Cl), Thane · Alfa Constructions
Promised for 30 Jun 2022, extended once to 15 Aug 2023 — and that date has passed without the project marked complete on MahaRERA.
4 years and 4 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 30 Jun 2022 to 15 Aug 2023 (1 extension certificate on record).
- !Risk: The latest completion date on record, 15 Aug 2023, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P51700018798
Is Sunset Heights 2 delayed?
Yes. MahaRERA records a promised completion of 30 Jun 2022, revised to 15 Aug 2023, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P51700018798. The completion date moved from 30 Jun 2022 to 15 Aug 2023.
Who is the promoter?
MahaRERA records Alfa Constructions as the promoter of P51700018798.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P51700018798.
Answers are generated from the record.
