Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredCompletion date passedMahaRERA status: Certificate Signed

P51700018665

Omkar Apartments · Badlapur (M Cl), Thane · Pinnacle Lifespaces

Promised for 30 Oct 2021 — that date has passed and MahaRERA does not mark the project complete.

5 years past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 30 Oct 2021, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate9 Sep 2021View

Orders 0

No MahaRERA order or list names this number.

Questions about P51700018665

Is Omkar Apartments delayed?

Yes. MahaRERA records a promised completion of 30 Oct 2021, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P51700018665.

Who is the promoter?

MahaRERA records Pinnacle Lifespaces as the promoter of P51700018665.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51700018665.

Answers are generated from the record.

Data through30 Oct 2026, 02:12SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology