Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P51700018601

Makarand-Bank Of Baroda Employees Co-Operative Housing Society Limited · Kalyandombivali (M Corp.), Thane · Prime Realtors

Promised for 30 Jun 2022, extended once to 31 Dec 2022 — and that date has passed without the project marked complete on MahaRERA.

4 years and 4 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Jun 2022 to 31 Dec 2022 (1 extension certificate on record).
  • Risk: The latest completion date on record, 31 Dec 2022, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate9 Sep 2021View
Extension certificate12 Aug 2022View

Orders 0

No MahaRERA order or list names this number.

Questions about P51700018601

Is Makarand-Bank Of Baroda Employees Co-Operative Housing Society Limited delayed?

Yes. MahaRERA records a promised completion of 30 Jun 2022, revised to 31 Dec 2022, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P51700018601. The completion date moved from 30 Jun 2022 to 31 Dec 2022.

Who is the promoter?

MahaRERA records Prime Realtors as the promoter of P51700018601.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51700018601.

Answers are generated from the record.