Aadinath Residency · Anjur, Thane · Shree Mahavir Enterpises
Promised for 30 Dec 2022, extended once to 30 Dec 2023 — and that date has passed without the project marked complete on MahaRERA.
3 years and 10 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 30 Dec 2022 to 30 Dec 2023 (1 extension certificate on record).
- !Caution: The latest completion date on record, 30 Dec 2023, has passed.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P51700017330
Is Aadinath Residency delayed?
Yes. MahaRERA records a promised completion of 30 Dec 2022, revised to 30 Dec 2023, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P51700017330. The completion date moved from 30 Dec 2022 to 30 Dec 2023.
Who is the promoter?
MahaRERA records Shree Mahavir Enterpises as the promoter of P51700017330.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P51700017330.