Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredExtendedMahaRERA status: Certificate Signed

P51700017157

Umiya Oasis · Mirabhayandar (M Corp.), Thane · Umiya Developers

Promised for 30 Dec 2029, extended to 30 Apr 2030, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Dec 2029 to 30 Apr 2030.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate9 Sep 2021View

Orders 0

No MahaRERA order or list names this number.

Questions about P51700017157

Is Umiya Oasis delayed?

Its completion moved from 30 Dec 2029 to 30 Apr 2030; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for P51700017157. The completion date moved from 30 Dec 2029 to 30 Apr 2030.

Who is the promoter?

MahaRERA records Umiya Developers as the promoter of P51700017157.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51700017157.

Answers are generated from the record.

Data through28 Oct 2026, 02:07SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology