RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P51700017019
Panvelkar Aangan Phase 1 · Washind (Ct), Thane · Crystal Realtors
Promised for 30 Dec 2023, extended once to 31 Dec 2027, which is still ahead.
The revised date is 4 years after the original promise.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 30 Dec 2023 to 31 Dec 2027 (1 extension certificate on record).
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P51700017019
Is Panvelkar Aangan Phase 1 delayed?
Its completion moved from 30 Dec 2023 to 31 Dec 2027; the revised date has not passed yet.
How many extensions has it had?
Deedo holds 1 extension certificate for P51700017019. The completion date moved from 30 Dec 2023 to 31 Dec 2027.
Who is the promoter?
MahaRERA records Crystal Realtors as the promoter of P51700017019.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P51700017019.
Answers are generated from the record.