RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P51700014444

Silver Estate · Dhavale, Thane · Nanda Kapildev Sharma

Promised for 31 Dec 2019, extended once to 30 Jun 2022 — and that date has passed without the project marked complete on MahaRERA.

6 years and 10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Dec 2019 to 30 Jun 2022 (1 extension certificate on record).
  • Risk: The latest completion date on record, 30 Jun 2022, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate4 Dec 2017View
Extension certificate2 Feb 2022View

Orders 0

No MahaRERA order or list names this number.

Questions about P51700014444

Is Silver Estate delayed?

Yes. MahaRERA records a promised completion of 31 Dec 2019, revised to 30 Jun 2022, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P51700014444. The completion date moved from 31 Dec 2019 to 30 Jun 2022.

Who is the promoter?

MahaRERA records Nanda Kapildev Sharma as the promoter of P51700014444.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51700014444.

Answers are generated from the record.

Data through25 Oct 2026, 02:15SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology