RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P51700014068

Skywards Regency · Mirabhayandar (M Corp.), Thane · Skywards Vision Developers

Promised for 1 Jul 2019, extended once to 31 Dec 2025 — and that date has passed without the project marked complete on MahaRERA.

7 years and 3 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 1 Jul 2019 to 31 Dec 2025 (1 extension certificate on record).
  • Risk: The latest completion date on record, 31 Dec 2025, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate7 Nov 2017View
Extension certificate1 Apr 2025View

Orders 0

No MahaRERA order or list names this number.

Questions about P51700014068

Is Skywards Regency delayed?

Yes. MahaRERA records a promised completion of 1 Jul 2019, revised to 31 Dec 2025, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P51700014068. The completion date moved from 1 Jul 2019 to 31 Dec 2025.

Who is the promoter?

MahaRERA records Skywards Vision Developers as the promoter of P51700014068.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51700014068.

Answers are generated from the record.

Data through25 Oct 2026, 02:14SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology