RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredCompletion date passed1 extensionMahaRERA status: Certificate Signed

P51700014064

Pineshire · Ambivali Tarf Chon, Thane · Aanya Residences

Promised for 31 Dec 2025 — that date has passed and MahaRERA does not mark the project complete.

10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Deedo holds 1 extension certificate for this registration.
  • Caution: The latest completion date on record, 31 Dec 2025, has passed.
  • Caution: 2 other MahaRERA orders name this registration.

Documents 2

Extension certificate16 May 2024View
Registration certificate16 May 2024View

Orders 2

Suo motu order

Suo motu order: Secretary, MahaRERA Versus KAMBAR CONSTRUCTIONS (Suo Motu Case No.209 of 2021) dated 8 June 2026.

8 Jun 2026 · may refer to a related project

View on MahaRERA
Suo motu order

Suo motu order: Secretary, MahaRERA Versus KAMBAR CONSTRUCTIONS (Suo Motu Case No.209 of 2021) dated 27 November 2025.

27 Nov 2025 · matched by RERA number

View on MahaRERA

Questions about P51700014064

Is Pineshire delayed?

Yes. MahaRERA records a promised completion of 31 Dec 2025, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P51700014064.

Who is the promoter?

MahaRERA records Aanya Residences as the promoter of P51700014064.

Is it on any MahaRERA regulatory list?

2 MahaRERA orders or lists name P51700014064.

Answers are generated from the record.

Data through24 Oct 2026, 02:00SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology