Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P51700013793

Shree Mahaganpati Tower · Titwala, Thane · Mahesh Shyamsundar Goyal

Promised for 31 Dec 2020, extended once to 21 Feb 2023 — and that date has passed without the project marked complete on MahaRERA.

5 years and 10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Dec 2020 to 21 Feb 2023 (1 extension certificate on record).
  • Risk: The latest completion date on record, 21 Feb 2023, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate25 Oct 2017View
Extension certificate8 Sep 2023View

Orders 0

No MahaRERA order or list names this number.

Questions about P51700013793

Is Shree Mahaganpati Tower delayed?

Yes. MahaRERA records a promised completion of 31 Dec 2020, revised to 21 Feb 2023, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P51700013793. The completion date moved from 31 Dec 2020 to 21 Feb 2023.

Who is the promoter?

MahaRERA records Mahesh Shyamsundar Goyal as the promoter of P51700013793.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51700013793.