RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P51700013602

Rohini · Khativali, Thane · Thilayaparambil Kumaran Joshi

Promised for 30 Jun 2021, extended once to 30 Dec 2024 — and that date has passed without the project marked complete on MahaRERA.

5 years and 4 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Jun 2021 to 30 Dec 2024 (1 extension certificate on record).
  • Risk: The latest completion date on record, 30 Dec 2024, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate18 May 2020View
Extension certificate9 Sep 2021View

Orders 0

No MahaRERA order or list names this number.

Questions about P51700013602

Is Rohini delayed?

Yes. MahaRERA records a promised completion of 30 Jun 2021, revised to 30 Dec 2024, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P51700013602. The completion date moved from 30 Jun 2021 to 30 Dec 2024.

Who is the promoter?

MahaRERA records Thilayaparambil Kumaran Joshi as the promoter of P51700013602.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51700013602.

Answers are generated from the record.