Deeplaxmi Height · Kalher (Ct), Thane · Deep Laxmi Developers
Promised for 31 Dec 2020, extended once to 30 Dec 2022 — and that date has passed without the project marked complete on MahaRERA.
5 years and 10 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 31 Dec 2020 to 30 Dec 2022 (1 extension certificate on record).
- !Caution: The latest completion date on record, 30 Dec 2022, has passed.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P51700012694
Is Deeplaxmi Height delayed?
Yes. MahaRERA records a promised completion of 31 Dec 2020, revised to 30 Dec 2022, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P51700012694. The completion date moved from 31 Dec 2020 to 30 Dec 2022.
Who is the promoter?
MahaRERA records Deep Laxmi Developers as the promoter of P51700012694.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P51700012694.
Answers are generated from the record.