RegisteredRevised date passed1 extensionMahaRERA status: Lapsed

P51700010181

Pentagon Enclave · Asangaon (Ct), Thane · Damji Hari Infrastructure Pvt Ltd

Promised for 31 Dec 2019, extended once to 31 Dec 2025 — and that date has passed without the project marked complete on MahaRERA.

6 years and 10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Dec 2019 to 31 Dec 2025 (1 extension certificate on record).
  • Risk: The latest completion date on record, 31 Dec 2025, has passed.
  • Caution: 10 other MahaRERA orders name this registration.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 169

Title report29 Jul 2017View
Encumbrance details29 Jul 2017View
Form B29 Jul 2017View
Form B29 Jul 2017View
Form 130 Jul 2017View
Form 130 Jul 2017View
Form 230 Jul 2017View
Form 230 Jul 2017View
Show all 169 documents
Form 230 Jul 2017View
Allotment letter30 Jul 2017View
Allotment letter30 Jul 2017View
Commencement certificate31 Jul 2017View
Registration certificate24 Aug 2017View
Form 118 Jun 2018View
Form 118 Jun 2018View
Form 118 Jun 2018View
Allotment letter23 Jul 2018View
Allotment letter23 Jul 2018View
Form 225 Jul 2018View
Form 225 Jul 2018View
Form 126 Dec 2018View
Form 126 Dec 2018View
Form 126 Dec 2018View
Form 226 Dec 2018View
Form 226 Dec 2018View
Form 226 Dec 2018View
Form 54 Feb 2019View
Form 119 Apr 2019View
Form 119 Apr 2019View
Form 119 Apr 2019View
Form 223 Apr 2019View
Form 223 Apr 2019View
Form 223 Apr 2019View
Form 126 Dec 2019View
Form 126 Dec 2019View
Form 126 Dec 2019View
Form 226 Dec 2019View
Form 226 Dec 2019View
Form 230 Dec 2019View
Form 17 Mar 2020View
Form 17 Mar 2020View
Form 17 Mar 2020View
Form 27 Mar 2020View
Form 27 Mar 2020View
Form 27 Mar 2020View
Form 123 Oct 2020View
Form 123 Oct 2020View
Form 123 Oct 2020View
Form 231 Oct 2020View
Form 231 Oct 2020View
Form 231 Oct 2020View
Form 124 Jun 2021View
Form 124 Jun 2021View
Form 124 Jun 2021View
Form 26 Jul 2021View
Form 26 Jul 2021View
Form 26 Jul 2021View
Commencement certificate26 Aug 2021View
Form 126 Aug 2021View
Form 126 Aug 2021View
Form 126 Aug 2021View
Form 226 Aug 2021View
Form 226 Aug 2021View
Form 226 Aug 2021View
Other26 Aug 2021View
Form 2A16 Sep 2021View
Form 2A16 Sep 2021View
Form 55 Oct 2021View
Form 55 Oct 2021View
Form 55 Oct 2021View
Form 19 Apr 2022View
Form 19 Apr 2022View
Form 19 Apr 2022View
Form 18 Jul 2022View
Form 18 Jul 2022View
Form 18 Jul 2022View
Form 28 Jul 2022View
Form 28 Jul 2022View
Form 28 Jul 2022View
Form 114 Sep 2023View
Form 114 Sep 2023View
Form 114 Sep 2023View
Form 214 Sep 2023View
Form 214 Sep 2023View
Form 214 Sep 2023View
Form 12 Nov 2023View
Form 12 Nov 2023View
Form 12 Nov 2023View
Form 12 Nov 2023View
Form 12 Nov 2023View
Form 12 Nov 2023View
Form 217 Nov 2023View
Form 217 Nov 2023View
Form 217 Nov 2023View
Form 522 Nov 2023View
Form 124 Nov 2023View
Form 224 Nov 2023View
Form 224 Nov 2023View
Other15 Dec 2023View
Form 2A28 Dec 2023View
Form 2A28 Dec 2023View
Form 2A28 Dec 2023View
Form 2A9 Jan 2024View
Form 2A9 Jan 2024View
Form 2A9 Jan 2024View
Other9 Jan 2024View
Other9 Jan 2024View
Other9 Jan 2024View
Other9 Jan 2024View
Other9 Jan 2024View
Other9 Jan 2024View
Other9 Jan 2024View
Other9 Jan 2024View
Form 512 Jan 2024View
Form B16 Jan 2024View
Encumbrance details3 Dec 2024View
Form 13 Dec 2024View
Form 13 Dec 2024View
Form 13 Dec 2024View
Form 13 Dec 2024View
Form 13 Dec 2024View
Form 13 Dec 2024View
Form 231 Dec 2024View
Form 231 Dec 2024View
Form 231 Dec 2024View
Form 215 Apr 2025View
Form 215 Apr 2025View
Form 215 Apr 2025View
Form B16 Apr 2025View
Other7 Jun 2025View
Form 11 Jul 2025View
Form 11 Jul 2025View
Form 11 Jul 2025View
Form 21 Jul 2025View
Form 21 Jul 2025View
Extension certificate18 Sep 2025View
Form 517 Apr 2026View
Form 517 Apr 2026View
Other24 Apr 2026View
Form 224 Apr 2026View
Form 124 Apr 2026View
Form 124 Apr 2026View
Form 224 Apr 2026View
Form 124 Apr 2026View
Form 224 Apr 2026View
OtherView
OtherView
Layout planView
Layout planView
Layout planView
Layout planView
Layout planView
Layout planView
Building planView
OtherView
OtherView
Allotment letterView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView

Orders 10

Show all 10 orders and lists

Questions about P51700010181

Is Pentagon Enclave delayed?

Yes. MahaRERA records a promised completion of 31 Dec 2019, revised to 31 Dec 2025, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P51700010181. The completion date moved from 31 Dec 2019 to 31 Dec 2025.

Who is the promoter?

MahaRERA records Damji Hari Infrastructure Pvt Ltd as the promoter of P51700010181.

Is it on any MahaRERA regulatory list?

10 MahaRERA orders or lists name P51700010181.

Answers are generated from the record.

Data through28 Oct 2026, 01:37SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology