RegisteredCompletion date passedMahaRERA status: Lapsed

P51700009701

Tulja Serenity Greens · Washind (Ct), Thane · Tuljai Construction Co

Promised for 30 Dec 2024 — that date has passed and MahaRERA does not mark the project complete.

1 year and 10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 30 Dec 2024, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 67

Title report31 Jul 2017View
Title report31 Jul 2017View
Title report31 Jul 2017View
Title report31 Jul 2017View
Title report31 Jul 2017View
Title report31 Jul 2017View
Encumbrance details31 Jul 2017View
Commencement certificate31 Jul 2017View
Show all 67 documents
Form B31 Jul 2017View
Form 131 Jul 2017View
Form 231 Jul 2017View
Allotment letter31 Jul 2017View
Form 127 Aug 2018View
Form 227 Aug 2018View
Commencement certificate3 Nov 2018View
Commencement certificate5 Nov 2018View
Form 19 Apr 2019View
Form 29 Apr 2019View
Form 29 Apr 2019View
Form 113 May 2019View
Form 113 May 2019View
Form 213 May 2019View
Form 213 May 2019View
Form 230 Aug 2021View
Other30 Aug 2021View
Registration certificate9 Sep 2021View
Form 518 Nov 2023View
Form 518 Nov 2023View
Form 518 Nov 2023View
Form 120 Nov 2023View
Form 120 Nov 2023View
Form 120 Nov 2023View
Form 120 Nov 2023View
Form 120 Nov 2023View
Form 120 Nov 2023View
Form 220 Nov 2023View
Form 220 Nov 2023View
Form 220 Nov 2023View
Form 520 Nov 2023View
Form 520 Nov 2023View
OtherView
Layout planView
Layout planView
Layout planView
Layout planView
Layout planView
Layout planView
Layout planView
Layout planView
Layout planView
Layout planView
Layout planView
Layout planView
Building planView
Building planView
Allotment letterView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P51700009701

Is Tulja Serenity Greens delayed?

Yes. MahaRERA records a promised completion of 30 Dec 2024, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P51700009701.

Who is the promoter?

MahaRERA records Tuljai Construction Co as the promoter of P51700009701.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51700009701.