Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P51700009177
Auralis The Twins · Thane (M Corp.), Thane · Deep Homes & Constructions Llp
Promised for 29 Feb 2020, extended once to 31 Jan 2021 — and that date has passed without the project marked complete on MahaRERA.
6 years and 8 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 29 Feb 2020 to 31 Jan 2021 (1 extension certificate on record).
- !Risk: The latest completion date on record, 31 Jan 2021, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P51700009177
Is Auralis The Twins delayed?
Yes. MahaRERA records a promised completion of 29 Feb 2020, revised to 31 Jan 2021, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P51700009177. The completion date moved from 29 Feb 2020 to 31 Jan 2021.
Who is the promoter?
MahaRERA records Deep Homes & Constructions Llp as the promoter of P51700009177.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P51700009177.
Answers are generated from the record.