Om Residency · Thane (M Corp.), Thane · Shree Kulswami Developers
Promised for 30 Jun 2019; MahaRERA reports the project completed.
The revised date is 1 year and 6 months after the original promise.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 30 Jun 2019 to 29 Dec 2020 (1 extension certificate on record).
- ✓Clear: MahaRERA reports the project as completed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 31
Orders 0
No MahaRERA order or list names this number.
Questions about P51700008682
Is Om Residency delayed?
MahaRERA reports it completed. Its promised completion date was 30 Jun 2019.
How many extensions has it had?
Deedo holds 1 extension certificate for P51700008682. The completion date moved from 30 Jun 2019 to 29 Dec 2020.
Who is the promoter?
MahaRERA records Shree Kulswami Developers as the promoter of P51700008682.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P51700008682.