Aabiel Heights · Mirabhayandar (M Corp.), Thane · Daichi Infra Llp
Promised for 28 Aug 2022, extended once to 10 Jul 2024 — and that date has passed without the project marked complete on MahaRERA.
4 years and 2 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 28 Aug 2022 to 10 Jul 2024 (1 extension certificate on record).
- !Risk: The latest completion date on record, 10 Jul 2024, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P51700006603
Is Aabiel Heights delayed?
Yes. MahaRERA records a promised completion of 28 Aug 2022, revised to 10 Jul 2024, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P51700006603. The completion date moved from 28 Aug 2022 to 10 Jul 2024.
Who is the promoter?
MahaRERA records Daichi Infra Llp as the promoter of P51700006603.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P51700006603.
Answers are generated from the record.