Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredCompletion date passedMahaRERA status: Certificate Signed

P51700004717

Anand Park D Wing · Mirabhayandar (M Corp.), Thane · R K Development

Promised for 31 Jul 2018 — that date has passed and MahaRERA does not mark the project complete.

8 years and 3 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 31 Jul 2018, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate9 Aug 2017View

Orders 0

No MahaRERA order or list names this number.

Questions about P51700004717

Is Anand Park D Wing delayed?

Yes. MahaRERA records a promised completion of 31 Jul 2018, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P51700004717.

Who is the promoter?

MahaRERA records R K Development as the promoter of P51700004717.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51700004717.

Answers are generated from the record.

Data through28 Oct 2026, 01:50SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology