RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P51700003913

Sai Nirvana · Kalyan, Thane · Shanklesha Constructions

Promised for 31 Dec 2019, extended once to 31 Mar 2024 — and that date has passed without the project marked complete on MahaRERA.

6 years and 10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Dec 2019 to 31 Mar 2024 (1 extension certificate on record).
  • Risk: The latest completion date on record, 31 Mar 2024, has passed.
  • Caution: 1 other MahaRERA order names this registration.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate6 Aug 2017View
Extension certificate21 Nov 2023View

Orders 1

Regulatory order

Regulatory order: PROJECT NAME:SAI NIRVANA (Regulatory Case No.91 of 2023) dated 6 November 2023.

6 Nov 2023 · matched by RERA number

View order →

Questions about P51700003913

Is Sai Nirvana delayed?

Yes. MahaRERA records a promised completion of 31 Dec 2019, revised to 31 Mar 2024, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P51700003913. The completion date moved from 31 Dec 2019 to 31 Mar 2024.

Who is the promoter?

MahaRERA records Shanklesha Constructions as the promoter of P51700003913.

Is it on any MahaRERA regulatory list?

1 MahaRERA order or list names P51700003913.

Answers are generated from the record.

Data through25 Oct 2026, 01:50SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology