Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredCompletion date passedMahaRERA status: Certificate Signed

P51700003742

Parshwa Hill · Ambarnath(M Cl), Thane · Jrv Construction Co

Promised for 30 Oct 2020 — that date has passed and MahaRERA does not mark the project complete.

6 years past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 30 Oct 2020, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate18 May 2020View

Orders 0

No MahaRERA order or list names this number.

Questions about P51700003742

Is Parshwa Hill delayed?

Yes. MahaRERA records a promised completion of 30 Oct 2020, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P51700003742.

Who is the promoter?

MahaRERA records Jrv Construction Co as the promoter of P51700003742.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51700003742.

Answers are generated from the record.

Data through25 Oct 2026, 02:09SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology