P51700003360
Nakshatra · Chikanghar, Thane · Abhishek Consttruction Co
Promised for 31 Jan 2021, extended once to 29 Sep 2022 — and that date has passed without the project marked complete on MahaRERA.
5 years and 9 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 31 Jan 2021 to 29 Sep 2022 (1 extension certificate on record).
- !Risk: The latest completion date on record, 29 Sep 2022, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P51700003360
Is Nakshatra delayed?
Yes. MahaRERA records a promised completion of 31 Jan 2021, revised to 29 Sep 2022, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P51700003360. The completion date moved from 31 Jan 2021 to 29 Sep 2022.
Who is the promoter?
MahaRERA records Abhishek Consttruction Co as the promoter of P51700003360.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P51700003360.
Answers are generated from the record.