Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P51600054801
Shree Kartikeya Phase 2 · Deolali (Cb), Nashik · Nirmiti Infra
Promised for 31 Oct 2026, extended to 28 Feb 2027, which is still ahead.
The revised date is 4 months after the original promise.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 31 Oct 2026 to 28 Feb 2027.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 1
Orders 0
No MahaRERA order or list names this number.
Questions about P51600054801
Is Shree Kartikeya Phase 2 delayed?
Its completion moved from 31 Oct 2026 to 28 Feb 2027; the revised date has not passed yet.
How many extensions has it had?
Deedo holds 0 extension certificates for P51600054801. The completion date moved from 31 Oct 2026 to 28 Feb 2027.
Who is the promoter?
MahaRERA records Nirmiti Infra as the promoter of P51600054801.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P51600054801.
Answers are generated from the record.