RegisteredMahaRERA status: Certificate Signed

P51600053381

B Square · Dindori, Nashik · Burad Buildcon

Promised for 31 Dec 2026 and not extended so far.

2 months to go until the promised date.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

    Documents 1

    Registration certificate27 Oct 2023View

    Orders 0

    No MahaRERA order or list names this number.

    Questions about P51600053381

    Is B Square delayed?

    Not so far. MahaRERA records a promised completion of 31 Dec 2026, which has not passed yet.

    How many extensions has it had?

    Deedo holds 0 extension certificates for P51600053381.

    Who is the promoter?

    MahaRERA records Burad Buildcon as the promoter of P51600053381.

    Is it on any MahaRERA regulatory list?

    No MahaRERA order or list that Deedo holds names P51600053381.

    Answers are generated from the record.

    Data through23 Oct 2026, 02:13SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology