Paradies Palms · Nashik · Sahyadri Construction
Promised for 30 Jun 2026, extended to 30 Oct 2026, which is still ahead.
The revised date is 4 months after the original promise.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 30 Jun 2026 to 30 Oct 2026.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 1
Orders 0
No MahaRERA order or list names this number.
Questions about P51600027376
Is Paradies Palms delayed?
Its completion moved from 30 Jun 2026 to 30 Oct 2026; the revised date has not passed yet.
How many extensions has it had?
Deedo holds 0 extension certificates for P51600027376. The completion date moved from 30 Jun 2026 to 30 Oct 2026.
Who is the promoter?
MahaRERA records Sahyadri Construction as the promoter of P51600027376.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P51600027376.
Answers are generated from the record.