RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P51600008562
Vijay Sneh · Nashik · Jaydevelopers
Promised for 31 Dec 2018; MahaRERA reports the project completed.
The revised date is 5 years and 7 months after the original promise.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 31 Dec 2018 to 30 Jul 2024 (1 extension certificate on record).
- ✓Clear: MahaRERA reports the project as completed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 28
Orders 0
No MahaRERA order or list names this number.
Questions about P51600008562
Is Vijay Sneh delayed?
MahaRERA reports it completed. Its promised completion date was 31 Dec 2018.
How many extensions has it had?
Deedo holds 1 extension certificate for P51600008562. The completion date moved from 31 Dec 2018 to 30 Jul 2024.
Who is the promoter?
MahaRERA records Jaydevelopers as the promoter of P51600008562.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P51600008562.
Answers are generated from the record.