The Metrozone Kingston D2 · Nashik (M Corp.), Nashik · Sanklecha Construction Private Limited
Promised for 31 Dec 2019, extended once to 31 Dec 2027, which is still ahead.
The revised date is 8 years after the original promise.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 31 Dec 2019 to 31 Dec 2027 (1 extension certificate on record).
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P51600005490
Is The Metrozone Kingston D2 delayed?
Its completion moved from 31 Dec 2019 to 31 Dec 2027; the revised date has not passed yet.
How many extensions has it had?
Deedo holds 1 extension certificate for P51600005490. The completion date moved from 31 Dec 2019 to 31 Dec 2027.
Who is the promoter?
MahaRERA records Sanklecha Construction Private Limited as the promoter of P51600005490.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P51600005490.